What involves working with stakeholders to create the document that formally authorizes a project?A project charter is a project planning document that sells the project to stakeholders and sponsors.
What is the name of the document that formally authorizes the existence of a project?The project charter is a document that officially starts a project or a phase. It formally authorizes the existence of the project and provides a reference source for the future.
Which term is used for a formal documented process that describes when and how official project documents may be modified?A change control system is a formal, documented process that describes when and how official project documents may be changed.
What process involves formal acceptance of the completed project scope by the stakeholders?Explanation. "Validate Scope" involves all of these outputs.
|