Dependencies are the relationships among tasks which determine the order in which activities need to be performed. There are four (4) types of dependency relationships.
Types of dependencies
Finish to Start | Predecessor must finish before Successor can start. [Land must be purchased before road building can start] | |
Start to Start | Predecessor must start before Successor can start. [Road excavating must start before Asphalt can be laid] | |
Finish to Finish | Predecessor must finish before Successor can finish. [Laying Asphalt must be complete before line painting can be completed] | |
Start to Finish | Predecessor must start before Successor can finish. [Road excavating must start before line painting can be completed] |
Dependencies are the relationships of the preceding tasks to the succeeding tasks. Tasks may have multiple preceding tasks and multiple succeeding tasks. The most common dependency relationship is a finish-to-start relationship. Task P (predecessor) must be finished before task S (successor) can start. The least common relationship is the start-to-finish relationship. Project Insight, project management software, supports all four dependency relationships.
Product Development Activity List
The chart above shows how a Product Development Activity List may look after the project team determines the task relationships. In our example, only finish-to-start relationships were used.
It is always easier to arrange all tasks in terms of a finish-to-start relationship and an 'as soon as possible' constraint. This dependency type is the easiest relationship for others to understand and will usually result in a longer than normal schedule. This gives the schedule more 'slack.' You may then utilize the other relationships as ways to shrink the duration of the overall schedule. If you use finish-to-start and as soon as possible, you will be able to change the schedule in Project Insight, project management software, with just a couple of mouse clicks.
<< Previous | Next >> Project resource allocation and resource management
Ready to Get Started?
Discover how PI® can help make your job easier. Start your free trial now!
question
In a PERT/CPM chart, each rectangular box, called a task box, has five sections that contain important information about a task.
question
When two or more concurrent tasks depend on a single prior task, the concurrent tasks are called ____ tasks.
question
For a project manager, reporting _____.
answer
includes informing management, users, and the project team about the progress of the project
question
____ is a time estimate the project manager makes for a task.
answer
The worst-case estimate The best-case estimate The probable-case estimate
question
System developers can initiate a formal project as early as the preliminary investigation stage, or later on, as analysis, design, and implementation activities occur.
question
Most risk identifications include a brief description of ____.
answer
who would be responsible for responding to a given risk
question
GanttProject can open files created with ____.
question
In a PERT/CPM chart, each task has which of the following ____.
question
Problems with timetables and project milestones can indicate ____.
answer
personality conflicts among team members
question
A ____ might involve maximums for one or more resources.
question
A PERT/CPM chart does not show the project as a network diagram with tasks connected by arrows.
question
Microsoft claims that Microsoft Project has the capability of ____.
answer
assign ownership of risks
question
Critical time is the amount of time that a task would be late without pushing back the completion date of the entire project.
question
Project management is dynamic and challenging, regardless of which software you use..
question
A _____ cannot be started until one or more other tasks are completed.
question
Gantt charts often are included in progress reports to show project status graphically.
question
_____ is a full-featured program that holds the dominant share of the project management software market.
question
When several tasks can start at the same time, each is called a(n) ____ task.
question
Project management software can highlight the series of tasks that form the critical path.
question
When an information system does not meet business requirements, causes might include ____
question
A event is a recognizable reference point that you can use to ____.
question
For a project manager, monitoring _____.
answer
requires guiding, supervising, and coordinating the project team's workload
question
Project management is dynamic and challenging, regardless of which software you use.
question
Tasks that are not on the critical path cannot be ignored.
question
Often, two or more concurrent tasks depend on a single prior task, which is called a successor task.
question
Although a Gantt chart provides more detailed information about a project, a PERT/CPM chart offers a rapid overview that graphically displays the timing, duration, and progress of each task
question
Gantt charts are an ideal tool for controlling a complex project because they provide plenty of detailed information.
question
Which of the following are metrics of a successful project ____.
answer
delivery of a product that satisfies users
question
Using a WBS allows you to manage a project as one large task
question
Which of the following is an example of an event?
answer
the start of user training conversion of system data completion of interviews
question
A risk ____ plan is a proactive effort to anticipate a risk and describe an action plan to deal with it.
question
Using prior experience to make time and cost estimates works best for large projects.
question
The accompanying figure shows task ____, which simplify a complex task by combining several activities.
question
In most systems analysis tasks, time and people are interchangeable.
question
When tasks must be completed one after another, they are called concurrent tasks.
question
Two or more concurrent tasks often depend on a single prior task, which is called a(n) ____ task
question
When two or more concurrent tasks depend on a single prior task, each of the concurrent tasks is called a predecessor task.
question
If team members lack experience with certain aspects of the required technology, temporary help might be obtained from IT consultants or part-time staff.
question
A ____ path includes all tasks that are vital to the project schedule.
question
When a project manager first recognizes that a project is in trouble, the options available to her include ____.
answer
delaying the project deadline
question
A(n) ____ chart displays complex task patterns and relationships
question
In GanttProject, unlike in Microsoft Project, you create tasks and durations, indicate dependencies, and assign resources.
question
When an information system does not meet business requirements, causes might include ____.
question
_____ is a full-featured program that holds the dominant share of the project management software market
question
A ____ is an event that could affect a project negatively.
question
The first step in creating a WBS is to ____.
question
If any task along the critical path falls behind schedule, the entire project is delayed.
question
In addition to tasks, every project has ____, which are reference points used to monitor progress and manage the project.
question
Project managers always must be aware of the ____ path, so they can monitor the vital tasks and keep the project on track.
question
Effective project reporting requires ____.
answer
strong communication skill
question
Project status meetings give project managers an opportunity to seek input and conduct brainstorming sessions.
question
The purpose of quantitative risk analysis is to understand the actual impact in terms of dollars, time, project scope, or quality.
question
When maintaining schedules, if enough ____ and frequent checkpoints exist, problems will be detected rapidly
question
When several tasks can take place at the same time, each is called a sequential task.
question
In any project, large or small, tasks depend on each other and must be performed in a sequence.
question
A project manager's scheduling function _____.
answer
involves staffing, which includes selecting the project team and assigning specific tasks to team members
question
A(n) ____ chart displays complex task patterns and relationships.
question
Microsoft's risk management model includes ____
answer
category, which specifies the risk type
question
Although a Gantt chart provides more detailed information about a project, a PERT/CPM chart offers a rapid overview that graphically displays the timing, duration, and progress of each task.
question
Structured walk-throughs take place throughout the SDLC and are called ____ reviews, depending on the phase in which they occur.
answer
code design testing
question
In the end, every successful information system must ____.
answer
support business requirements stay within budget be completed on time
question
A project manager, or project leader, usually is a senior systems analyst or an IT department manager if the project is large.
question
PERT/CPM is called a(n) ____ technique, because it analyzes a large, complex project as a series of individual tasks.
question
Most managers recognize that problems do occur on most projects; it is better to alert management sooner rather than later.
question
The Apptivo ____ is free of charge with unlimited duration.
question
A project triangle shows three legs: _____.
answer
project cost, scope, and time